Project Name: Alle-Catt Wind

Developer: Invenergy
Proposed Number of Turbines: 120
MW: 380 MW
Towns: Arcade, Centerville, Farmersville, Freedom, New Hudson, Rushford, and Yorkshire
County: Allegany, Cattaraugus, and Wyoming
Article 10: PSC case number – 17-F-0282
Status: Preliminary Scoping Statement submitted – January 22, 2018

Link to current articles:

Project Name: Arkwright Summit Wind

Developer: EDP Renewables
Number of Turbines: 36
MW: 78 MW
Town: Arkwright
County: Chautauqua
SEQR: State Environmental Quality Review
Status: online since 2018
Developer: website 
This project was permitted outside of the Article 10 process
Citizen groups:

Link to current articles:

You Tube Videos:

Project Name: Baron Winds

Developer: Everpower
Proposed Number of Turbines: 76
MW: 300 MW
Towns: Avoca, Cohocoton, Dansville, Fremont, Hornellsville, Howard, & Wayland
County: Steuben
Article 10: PSC case number – 15-F-0122
Status: Application deemed compliant – August 29, 2018

Link to current articles:

Project Name: Cassadagua Wind

Developer: Everpower
Proposed Number of Turbines: 48
MW: 126 MW
Towns: Arkwright, Charlotte, Cherry Creek, Stockton
County: Chatauqua
Article 10: PSC case number – 14-F-0490
Status: Application approved – January 17, 2018

Link to citizen groups:

Link to current articles:

Project Name: Galloo Island Wind Energy

Developer: Apex Clean Energy
Proposed Number of Turbines: 30
MW: 110 MW
Towns: Henderson, Hounsfield
County: Jefferson
Article 10: PSC case number – 15-F-0327
Status: Application deemed compliant – July 6, 2018

Link to citizen groups:

Link to current articles:

 

Project Name: Heritage Wind

Developer: Apex Clean Energy
Proposed Number of Turbines: 47
MW: 200 MW
Town: Barre
County: Orleans
Article 10: PSC case number – 16-F-0546
Status: Preliminary Scoping Statement submitted – March 16, 2018

Link to citizen groups:

Link to current articles:

Project Name: High Bridge Wind

Developer: Calpine Corporation
Proposed Number of Turbines:
MW: 100 MW
Towns: Guilford
County: Chenango
Article 10: PSC case number – 18-F-0262
Status: Public Involvement Plan submitted – June 28, 2018

Project Name: Jerico Rise Wind Farm

Developer: EDP Renewables
Number of Turbines: 37
MW: 78 MW
Towns: Bellmont & Chateaugay
County: Franklin
SEQR: State Environmental Quality Review
Status: online since 2016
Developer:  Website
This project was permitted outside of the Article 10 process

Link to citizen groups:

Link to current articles:

Link to video:

Project Name: Lighthouse Wind

Developer: Apex Proposed Number of Turbines: 45-70 MW: 200 MW Towns: Somerset & Yates Counties: Niagara & Orleans Article 10: PSC case number – 14-F-0485 Status: Preliminary Scoping Statement submitted – November 23, 2015

Link to citizen group:

Link to current articles:

Project Name: Number Three Wind

Developer: Invenergy
Proposed Number of Turbines: 43
MW: 105.8 MW
Towns: Lowville, Harrisburg
County: Lewis
Article 10: PSC case number – 16-F-0328
Status: Application completed – September 28, 2018

Links for more information: